The Schedule
Schedule Fall 2005
3 October
A spec Review-Architecture
10 October
Prototypes, Meeting with Team Leaders, Team Members
Issue 1: message passing, object passing?
Issue 2: Questions with the architecture and Design and Discussion of Designs of Teams.
17 October
B-Spec Review
24 October
(Today)
Status Report: 5-10 mins of talk about the status of the teams, work and discussion+issues resolved
Component Management and Communication System Team: Pushkar Pathak
Repository Server Team: Jeetendra Kukreja
Test Bed Server Team: Jiaqi Yu
Repository and Test Bed Server Client Team: Pooja Desai
Test Team: Sriram Ramamurthy
BSpecs DUE!
31 October
Design Review
Test Plans
7 November
Integration Report
RT Client-Communication-> Pushkar Pathak
Repository Server-Communication-> Atanu Panda
14 November
Integration Report
RT Client-Communication-> Kevin Alden
TestBed Server-Communication -> Pooja Desai
21 November
Test Readiness Review and Integration Summary
28 November
Final Test Meetings & Reviews
2 December
Qualification Test
12 December
Final Product Delivery